What's Next?
Works to begin
Pre-commencement works will begin at the reserve in the coming weeks and will include:
- the removal of vegetation within the building zone
- relocation of existing Coliban Water infrastructure
- consolidation of existing power infrastructure
- completion of regulatory safety checks.
How did we get here?
Council Meeting | Action |
---|---|
16 May 2023 | Awarded all-gender pavilion construction contract to local builder BLR Provincial Pty Ltd. |
15 March 2023 | Issued Planning Permit PA303/2022 for the construction of all gender change facilities, associated landscaping and the removal of vegetation at Bill Woodfull Reserve (subject to a number of conditions) |
20 September 2023 | Endorsed designs for new Bill Woodfull Recreation Reserve All Gender Change Facilities subject to planning approval |
Background
Project Background
Following community consultation throughout 2022, Maree Edwards MP announced in October that Council had successfully bid for State Government funding to deliver:
- a new all gender pavilion to service netball and tennis participants
- lighting upgrades for the oval and netball courts.
Designs
The designs for the projects were endorsed by Council in September 2022.
Lighting: the preferred design solution will see four 24m poles installed for oval sports lighting.
Pavilion: designs have been informed by advice from Council’s Heritage Advisor and the Maldon Design Guidelines.