What's Next?

Works to begin

Pre-commencement works will begin at the reserve in the coming weeks and will include:

  • the removal of vegetation within the building zone
  • relocation of existing Coliban Water infrastructure
  • consolidation of existing power infrastructure
  • completion of regulatory safety checks.

How did we get here?

Council MeetingAction
16 May 2023Awarded all-gender pavilion construction contract to local builder BLR Provincial Pty Ltd.
15 March 2023Issued Planning Permit PA303/2022 for the construction of all gender change facilities, associated landscaping and the removal of vegetation at Bill Woodfull Reserve (subject to a number of conditions)
20 September 2023Endorsed designs for new Bill Woodfull Recreation Reserve All Gender Change Facilities subject to planning approval

Background

Project Background

Following community consultation throughout 2022, Maree Edwards MP announced in October that Council had successfully bid for State Government funding to deliver:

  • a new all gender pavilion to service netball and tennis participants
  • lighting upgrades for the oval and netball courts.

Designs

The designs for the projects were endorsed by Council in September 2022.

Lighting: the preferred design solution will see four 24m poles installed for oval sports lighting.

Pavilion: designs have been informed by advice from Council’s Heritage Advisor and the Maldon Design Guidelines.

Look at the designs

Endorsed by Council - September 2022