Works set to begin

21 September 2023

Works to begin

Pre-commencement works will begin at the reserve in the coming weeks and will include:

  • the removal of vegetation within the building zone
  • relocation of existing Coliban Water infrastructure
  • consolidation of existing power infrastructure
  • completion of regulatory safety checks.

How did we get here?

Council MeetingAction
16 May 2023Awarded all-gender pavilion construction contract to local builder BLR Provincial Pty Ltd.
15 March 2023Issued Planning Permit PA303/2022 for the construction of all gender change facilities, associated landscaping and the removal of vegetation at Bill Woodfull Reserve (subject to a number of conditions)
20 September 2023Endorsed designs for new Bill Woodfull Recreation Reserve All Gender Change Facilities subject to planning approval